Tuesday, June 29, 2010

June 29th Update

This picture below displays the front and side view of the academic building which is the Elementary library. The windows will not be easily detected when the building is completed because both the front and side walls of the Elementry library will be covered with a tinted glass in the future, giving it a full glass affect.


Here is a picture of the front of the Academic building which from left to right will be the future Elementary Library, school entrance, atrium, parent lounge, PTA offices, and a conference room on the right corner. That is what is located directly behind this front wall but behind those spaces on this same floor will also be the future admissions office, testing area, Early Learning Center, Spirit store and the school Cafe.


This picture is the current status of the athletic / admissions building area. All of the concrete piles have been driven in the ground until they rested on the bedrock below and the piles were then cut off even with the ground, this provides a sturdy foundation for the gymnasium building. The next step will be to work on placing a drainage system in this area prior to a light coat of concrete called puhding which will support the rebar work in preperation of the 1 meter concrete mat that will be poured in this area to form the floor for the future gym and office space for the P.E. teachers and athletic director.


This picture displays the iron work of the PAC elevator shaft on the left side of the picture and the future lobby area out side the Performing Arts Center below. The red colored metal on the right is the base for the balcony above the lobby area. This balcony is an area that is accessed from ground level parking lot which will offer access to the elevator or the stairs to take people to the lobby area as well as the Performing Arts Center.




Sunday, June 27, 2010

Update on June 26 of Dorm building

This picture is taken from the back side of the cafeteria / school kitchen and dorm building from the north east corner of the campus. It shows the progress on this building which has reached the first floor, which will be one of five dorms located in this building.

This is a view from the future soccer field area of the construction of the cafeteria / dorm which is a frontal view of the ground floor cafeterias and the process of the first floor which when completed will be one dorm out of five to be built here. The first floor will more than likely be designated the Middle School Dorm leaving 2nd - 5th floors as High School Dorms.



Monday, June 21, 2010

Walkin freezer and frigerator space on the back side of the kitchen which will create a wall adjacent with future eastside cafeteria serving line.
Boarding temporary office space located in the far east end of the east side cafeteria.

Front view of the westside cafeteria with walls going up



View of the campus from the orchard hill top




Kitchen space located between the two cafeterias that will give the food service department more space to operate in the future.






Wednesday, June 9, 2010

June 10 update of the campus progress









Here is a picture of the campus from the orchard hill top accross the road on June 9



Here is a picture of the iron work that is completed in the PAC area and is now waiting on the concrete to be poured 1 meter thick to create the flooring for the PAC area.











This is a view below of the Fine Arts corner, the PAC lobby area, and the pull out bleacher seating area that will be multipurpose space for the Fine Arts department. The rebar work is completed and waiting on the concrete to be poured.











Tuesday, June 8, 2010

June 9th working on walls for ELC area and PAC concrete due soon

This is a view of the PAC area where all the rebar work is waiting on a 1 meter thick
concrete mat to be poured this week.


Thursday, June 3, 2010

Updates from June 4th

Here below is the frame work of the future Spirit store which is located to the left of the Admissions office.



Below is a picture of an official visit made to the site by the Dorm Committee members who met for the final quarter meeting and were interested in taking the time to see the progress on the site.


Below is a view of the future classroom side of the Atrium taken form the Elementary Administration office area.




Below concrete is being poured to complete the flooring foundation of the cafeteria and kitchen areas.