Friday, October 29, 2010

Renditions and general snap shots

Here is a picture of the tennis court area at far east side of our campus where the plans are being made for 3 single courts and 2 doubles courts. The wall will be smoothed out to become the practice wall for our teams. The fact is that the surface of the tennis courts are to be even with the top of the sloped concrete at the base of the wall. There will be an additional fence attached later to the top of the wall to keep our neighbors from falling into our court area.





Men at work getting piping into the second floor above the Atrium area of the academic building in order to keep the indoors work on track.



Here is a projected rendition of the recreation area of a dorm and these pipes will be covered by the back wall in the artist concept picture. The rooms to the left side in the picture are the study room at the deep left of the picture, and the dorm office is adjacent on the left of the recreation room.


Here is a rendition of the dorm parents living room and apartment entrance to the right of the kitchen area.





Visitors come to see the site to make sure that there is a new campus being built

Two fine ladies who worked hard and helped set up Interior Design renditions all over the new campus for the October planned staff and parent visits to the new campus site. This particular rendition is the westside cafeteria rendition.





The Headmaster and his wife made a visit to the new campus site to check out the progress of the construction project on Friday afternoon on October 29. They are standing at the mouth of the hallway of the north side classrooms, with the future teachers lounge to be built to their right and second floor of the secondary library to their left. This is the north side of the third floor of a planned five story academic classroom wing.



Some Dorm Staff who insisted on checking to see if Brent was really at the site.

An old man and some of the parents that visited the campus this week to see the progress of our new school .



The site manager told the Headmaster that he felt that all the buildings on site would be in the dry with their roofs on by Christmas, which will be a nice Christmas present to us all.


A view of the 5th and from the 5th

Here is a view from the fifth floor looking down at the fly loft of the PAC.






A view below of the making of the fifth and final floor of the dorm building that will tower over the soccer field and have a wonderful view of the neighboring golf course even into the night.


Here is the view of the creation of the High School Art labs which will be located on the 5th and final floor of the west side of the Academic building.



This is a view of the fifth floor patio where the art students will team with their tools to capture the landscapes on canvas for the rest of us to admire.






Activity Center, Gym and Admin building getting some back fill

The basement gym exterior wall has three coats of sealer on it and a 50mm thick foam insulation bonded to the wall with drain board attached to the insulation and as you can see the back filling of soil has begun on the south side which is being packed down as they go.






This is a view the ground level lobby of the Administration and Athletic building which will eventually lead up to the finance office and then one more floor up which will be the top floor and will be the offices of the Development and Marketing Directors offices as well as the offices of the Assitant Headmaster and Headmaster. The lobby level is the same level that the nurses clinic, Health classroom and where the Activity Center will be located on.
If one goes down the stairs from the lobby level you will enter into a hallway leading to the fitness center which is located next to a large multiple Physical Education teacher work area, and both overlook the show case gym which will be large enough for two full court basket ball games going sideways with a curtain to divide them with automated bleachers on the south side. The locker rooms are on the basement floor as well, right off the court area.





Tuesday, October 19, 2010

School View

Front view of the school

Art Deck With A View

View from the future art deck area
Fifth floor and the future art students' deck work area

Fifth floor outside art deck


Alumni Visitors In Town

Alumni come to check out the progress on the new school
(Hans Cho, David Sur, Tim Gallagher, Inwook Park, and Dennis Kim)

Sky Loft

A view of inside the sky loft

Conduit

A maze of conduit that will soon be covered with concrete

Pouring Concrete

Concrete being poured on the fifth floor of the academic building


High School Classrooms

The third floor of the high school where classrooms will soon be constructed

Academic Bldg

The third floor of the academic building being prepared for next week's concrete pour

Academic Bldg Staircase

Going up? Atrium view of the ascending central staircase in the academic building

Middle School Commons Area

A view from the first floor to the commons area of the middle school

Atrium

Looking in on the future atrium area

Science Lab Area

The latest view of the future high school science lab area

Sunday, October 17, 2010

Activity Center

Home of the lobby area in the future Activity Center
Picture taken from the lobby area of the Activity Center, but in the near future a floor will prevent such a view and only a fly on the basement gym ceiling can see it
Stairs ascending to the Activity Center lobby area



Campus View

A view from the stairwell of the administrative and athletic building

Performing Arts Center

Bleacher area to accommodate a full house in the PAC or drama classrooms during school
Lobby area in front of the PAC
Fixed seating area in the PAC
Picture from the stage looking out on the future fixed seating area
Future storage area and dressing rooms next to the stage area
Lumber elevator
Another view of the lumbar elevator to the stage building room











Gym Walls

Insulation and drain board bonded to the entire perimeter of the exterior basement gym walls with two coats of sealant between the concrete and insulation

Clinic

Future clinic for the school and dorm adjacent to the Activity Center lobby area

Sunday, October 10, 2010

View of the campus

View of the new campus taken from the orchard

Academic Building

Fourth floor view of the work being done on the third floor/northern portion of the academic building
Area between the east end of the northern portion of the academic building and the west side of the athletic and administration building

View taken from the courtyard looking at the western side of the academic building


Northern section of the academic building working on the third floor while the western section is working on the 5th floor







Athletic Building Stairs

The stairs from B1 of the athletic building to the first floor where the health classrooms, clinic, and activity center lobby will be located